Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 423123.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $7,000.00
Current Penalty: $3,000.00
Issuance Date: 10/29/2012
Nr Instances: 1
Nr Exposed: 5
Abatement Date: 10/30/2012
Gravity: 10
Report ID: 0317000
Contest Date:
Final Order: 11/15/2012
Related Event Code (REC): V
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/15/2012 | $3,000.00 | 10/30/2012 | Serious | |
Penalty | Z: Issued | 10/29/2012 | $7,000.00 | 10/30/2012 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as follows: a) Jobsite - 2000 Parrish Street - The working levels of the 4th & 5th levels of the tubular welded scaffold were not fully planked between the front and rear uprights. Observed on about 4/30/12.