Violation Detail
Standard Cited: 5A0001 OSH Act General Duty Paragraph
Inspection Nr: 314092818
Citation: 01003
Citation Type: Serious
Abatement Status: I
Initial Penalty: $5,390.00
Current Penalty: $3,234.00
Issuance Date: 09/08/2011
Nr Instances: 3
Nr Exposed: 4
Abatement Date: 09/13/2011
Gravity: 10
Report ID: 0418400
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 09/29/2011 | $3,234.00 | 09/13/2011 | Serious | |
| Penalty | Z: Issued | 09/08/2011 | $5,390.00 | 09/13/2011 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard: BURNS
P.L. 91-596 Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to the hazards of being burned from a fire and or not being able to exit the building due to non-functioning sprinkler system: A) T- Shed 1, on or about March 28, 2011, the sprinkler system for this area has not been inspected in over a year and the pressure gage was near 0, the sprinkler systems, exposing employees to a hazard of being burned while trying to exit the building during a fire. B) T- Shed 2, on or about March 28, 2011, the sprinkler system for this area has not been inspected in over a year and the pressure gage was near 0, the sprinkler systems, exposing employees to a hazard of being burned while trying to exit the building during a fire. C) T- Shed 3, on or about March 28, 2011, the sprinkler system for this area has not been inspected in over a year and the pressure gage was near 0, the sprinkler systems, exposing employees to a hazard of being burned while trying to exit the building during a fire. One feasible and acceptable abatement method to correct this hazard is to have the sprinkler system inspected according to Table 5.1.1.2 of NFPA 25. ABATEMENT CERTIFICATION IS NOT REQUIRED.TION