Violation Detail
Standard Cited: 19100119 D03 II Process safety management of highly hazardous chemicals.
Inspection Nr: 314091497
Citation: 01003
Citation Type: Serious
Abatement Status: X
Initial Penalty: $6,930.00
Current Penalty: $4,197.00
Issuance Date: 05/16/2011
Nr Instances: 3
Nr Exposed: 10
Abatement Date: 08/31/2011
Gravity: 10
Report ID: 0418400
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
Substance: D177
Substance: 1680
Substance: 0675
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/09/2011 | $4,197.00 | 08/31/2011 | Serious | |
| Penalty | Z: Issued | 05/16/2011 | $6,930.00 | 06/30/2011 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard: CHEMNEP
29 CFR 1910.119(d)(3)(ii): The employer did not document that the equipment in the process complied with recognized and generally accepted good engineering practices: a)In the Telone repackaging area, on or about December 8, 2010 and at times prior to, the employer did not document that the equipment complied with generally accepted good engineering practices for the Telone repackaging process, resulting in fire and chemical hazards. Sections of the Telone process piping were constructed of galvanized steel, an incompatible material; compressed air was used to transfer the Telone; the physical condition of the Telone storage tanks was undetermined, and the Telone storage tanks' pressure relief valves were not vented to a safe location. b)DELETED FOR ISA SETTLEMENT. LBD 6.13.11 c)INSTANCE REMOVED AND ADDED TO CITATOIN 2 ITEM 5 FOR ISA SETTLEMENT. LBD 6.13.11 ABATEMENT CERTIFICATION AND DOCUMENTATION ARE REQUIRED.TION