Violation Detail
Standard Cited: 19100147 D The control of hazardous energy (lockout/tagout).
This violation item has been deleted.
Inspection Nr: 1854908.015
Citation: 01003
Citation Type: Serious
Abatement Status:
Initial Penalty: $16,550.00
Current Penalty: $0.00
Issuance Date: 01/21/2026
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 02/25/2026
Gravity: 10
Report ID: 0522000
Contest Date:
Final Order: 02/18/2026
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/18/2026 | $0.00 | 02/25/2026 | Serious | |
| Penalty | Z: Issued | 01/21/2026 | $16,550.00 | 02/25/2026 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.147(d): Application of control. The established procedures for the application of energy control (the lockout or tagout procedures) shall cover the following elements and actions and shall be done in the following sequence: (1) Preparation for shutdown. Before an authorized or affected employee turns off a machine or equipment, the authorized employee shall have knowledge of the type and magnitude of the energy, the hazards of the energy to be controlled, and the method or means to control the energy. (2) Machine or equipment shutdown. The machine or equipment shall be turned off or shut down using the procedures established for the machine or equipment. An orderly shutdown must be utilized to avoid any additional or increased hazard(s) to employees as a result of the equipment stoppage. (3) Machine or equipment isolation. All energy isolating devices that are needed to control the energy to the machine or equipment shall be physically located and operated in such a manner as to isolate the machine or equipment from the energy source(s). (4) Lockout or tagout device application. (4)(i) Lockout or tagout devices shall be affixed to each energy isolating device by authorized employees. (5) Stored energy. (5)(i) Following the application of lockout or tagout devices to energy isolating devices, all potentially hazardous stored or residual energy shall be relieved, disconnected, restrained, and otherwise rendered safe. (5)(ii) If there is a possibility of re-accumulation of stored energy to a hazardous level, verification of isolation shall be continued until the servicing or maintenance is completed, or until the possibility of such accumulation no longer exists. (6) Verification of isolation. Prior to starting work on machines or equipment that have been locked out or tagged out, the authorized employee shall verify that isolation and de-energization of the machine or equipment have been accomplished. a) On or about October 9, 2025, employees were exposed to amputation hazards in that the employer did not ensure (d)(1) through (d)(6) were followed by each employee to shut down the ENCHU EV360T at Line2-20 in an orderly manner before performing servicing or maintenance. An employee servicing the equipment without previously completing the required shutdown sequence got a finger caught-in a collet inside a spindle that kept dropping a tool; causing a partial amputation on left index finger.
Translate