Standard Cited: 19100119 G01 I Process safety management of highly hazardous chemicals.
Inspection Nr: 1809314.015
Citation: 01003
Citation Type: Serious
Abatement Status:
Initial Penalty: $16,550.00
Current Penalty: $16,550.00
Issuance Date: 08/18/2025
Nr Instances: 1
Nr Exposed: 180
Abatement Date: 10/03/2025
Gravity: 10
Report ID: 0316300
Contest Date: 09/10/2025
Final Order:
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | C: Contested | 09/10/2025 | $16,550.00 | 10/03/2025 | Serious | |
| Penalty | Z: Issued | 08/18/2025 | $16,550.00 | 10/03/2025 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.119(g)(1)(i):The employer did not train each employee in the operating procedures as specified in paragraph (f) of 29 CFR 1910.119. a) Green Lines Multi Base Process, Remote Blocker Building: On or about February 28, 2025, and at times prior thereto, the employer did not ensure employees were trained on the procedure for Preblocking Propellant by Remote Operations, for sections including but not limited to, operations, normal operations, normal shutdown, emergency shutdown, startup following a turnaround or after emergency shut down and consequence of deviations. Employee(s) were exposed to the hazards associated with the manufacturing of explosives such as burns and possible death from fire and explosions. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.