Violation Detail
Standard Cited: 19100305 A02 IX Wiring methods, components, and equipment for general use.
Inspection Nr: 1802516.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,837.00
Current Penalty: $2,300.00
Issuance Date: 04/10/2025
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 04/22/2025
Gravity: 1
Report ID: 0317700
Contest Date:
Final Order: 04/30/2025
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/30/2025 | $2,300.00 | 04/22/2025 | Serious | |
| Penalty | Z: Issued | 04/10/2025 | $2,837.00 | 04/22/2025 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.305(a)(2)(ix): All lamps for general illumination were not protected as required and/or brass shell, paper-lined sockets, or other metal-cased sockets were used when the shell was not grounded: a) Main Building - On or about February 5, 2025, employees were exposed to a shock hazard when operating the Big Press from a clamp lamp shell that was not grounded nor was the light bulb protected against accidental damage. ABATEMENT CERTIFICATION REQUIRED
Translate