Standard Cited: 19260600 A06 IV Equipment.
This violation item has been deleted.
Inspection Nr: 1784650.015
Citation: 01003
Citation Type: Serious
Abatement Status:
Initial Penalty: $16,550.00
Current Penalty: $0.00
Issuance Date: 02/05/2025
Nr Instances: 1
Nr Exposed: 13
Abatement Date: 03/06/2025
Gravity: 10
Report ID: 0636900
Contest Date: 02/19/2025
Final Order: 06/09/2025
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 06/09/2025 | $0.00 | 03/06/2025 | Serious | |
Penalty | C: Contested | 02/24/2025 | $16,550.00 | 03/06/2025 | Serious | |
Penalty | Z: Issued | 02/05/2025 | $16,550.00 | 03/06/2025 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.600(a)(6)(iv): A person was not designated to observe clearance of the equipment and give timely warning for all operations where it is difficult for the operator to maintain the desired clearance by visual means: On or about October 21, 2024, the employer directed a concrete pour using a Schwing 36-meter concrete pump truck near an overhead electrical transmission line without using a spotter to maintain a safe operating distance from the high voltage overhead electrical hazard of 14.4KV.