Standard Cited: 19260859 G Mechanical demolition.
Inspection Nr: 1757305.015
Citation: 01003
Citation Type: Serious
Abatement Date: 12/04/2024 5
Initial Penalty: $16,131.00
Current Penalty: $12,000.00
Issuance Date: 11/07/2024
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0419400
Contest Date:
Final Order: 12/06/2024
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/06/2024 | $12,000.00 | 12/04/2024 | Serious | |
Penalty | Z: Issued | 11/07/2024 | $16,131.00 | 12/04/2024 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.859(g): During demolition, continuing inspections by a competent person were not made as the work progressed to detect hazards resulting from weakened or deteriorated floors, or walls, or loosened material. Employees were also permitted to work where such hazards existed without being corrected by shoring, bracing, or other effective means. (a) Loading yard - On or about June 25, 2024, the employer did not ensure that continuing inspections were done during the demolition of silos that would detect loosened material exposing employees to struck by hazards.