Violation Detail
Standard Cited: 19100252 A03 II General requirements.
Inspection Nr: 1751979.015
Citation: 01003
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $16,131.00
Current Penalty: $10,978.50
Issuance Date: 11/18/2024
Nr Instances: 1
Nr Exposed: 1
Abatement Date:
Gravity: 10
Report ID: 0111100
Contest Date: 12/16/2024
Final Order: 12/30/2024
Related Event Code (REC): A
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 12/30/2024 | $10,978.50 | Serious | ||
| Penalty | C: Contested | 12/30/2024 | $16,131.00 | Serious | ||
| Penalty | Z: Issued | 11/18/2024 | $16,131.00 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.252(a)(3)(ii): All hollow spaces, cavities, or containers were not vented to permit the escape of air or gases before preheating, cutting, or welding was performed, and inert gas was not used: Welding Area - On May 31, 2024, an employee was fatally injured while welding on a diesel tank that had not been vented or purged with an inert gas.