Violation Detail
Standard Cited: 19100269 D02 IV B Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1748916.015
Citation: 01003
Citation Type: Serious
Abatement Status:
Initial Penalty: $16,131.00
Current Penalty: $16,131.00
Issuance Date: 11/13/2024
Nr Instances: 2
Nr Exposed: 4
Abatement Date: 12/10/2024
Gravity: 10
Report ID: 0625400
Contest Date: 10/29/2024
Final Order:
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | C: Contested | 02/12/2025 | $16,131.00 | 12/10/2024 | Serious | |
Penalty | Z: Issued | 11/13/2024 | $16,131.00 | 12/10/2024 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.269(d)(2)(iv)(B): The procedure did not clearly and specifically outline the procedural steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy: On or about May 13, 2024, at the Crusher Bypass Chute; the energy control procedure for the bypass chute cleaning task was missing the energy source isolation procedures.