Violation Detail
Standard Cited: 19100146 D03 III Permit-required confined spaces
Inspection Nr: 1739222.015
Citation: 01003
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $16,131.00
Current Penalty: $12,098.25
Issuance Date: 08/12/2024
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 09/06/2024
Gravity: 10
Report ID: 0729700
Contest Date:
Final Order: 09/10/2024
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/10/2024 | $12,098.25 | 09/06/2024 | Other | |
Penalty | Z: Issued | 08/12/2024 | $16,131.00 | 09/06/2024 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.146(d)(3)(iii):Under the permit-required confined space program required by 29 CFR 1910.146(c)(4), the employer did not develop and implement the means, procedures, and practices necessary for safe permit space entry operations. On March 26-27, 2024, contractors managed by Merit Energy, were exposed to combustible hazards in that the gun barrel was not identified as a confined space and the contractors were not made aware that the location was a permit confined space prior to work being accomplished inside the tank after the portal cover was removed, and prior to entry into the gun barrel tank.