Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 1719540.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,531.00
Current Penalty: $3,318.60
Issuance Date: 06/25/2024
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 07/15/2024
Gravity: 5
Report ID: 0418800
Contest Date:
Final Order: 07/19/2024
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/19/2024 | $3,318.60 | 07/15/2024 | Serious | |
| Penalty | Z: Issued | 06/25/2024 | $5,531.00 | 07/15/2024 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii): On or about 1/4/2024 and at times prior, at Building #88, 107 Spring Lake Court, Vero Beach, Florida 32962, employees were exposed to a 7-foot fall hazard while performing concrete restoration work from a tubular welded frame scaffold that was not fully planked.