Violation Detail
Standard Cited: 19260095 A Criteria for personal protective equipment.
Inspection Nr: 1717764.015
Citation: 01003
Citation Type: Serious
Abatement Date: 07/01/2024 5
Initial Penalty: $4,056.00
Current Penalty: $4,056.00
Issuance Date: 06/04/2024
Nr Instances: 1
Nr Exposed: 5
Related Event Code (REC): I
Gravity: 5
Report ID: 0316700
Contest Date:
Final Order: 07/08/2024
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 06/04/2024 | $4,056.00 | 07/01/2024 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.95(a):Protective equipment, including personal protective equipment for eyes, face, head, and extremities, protective clothing, respiratory devices, and protective shields and barriers, were not provided: (a) 530 Pine Street, Lykens, PA, Roof, - Employees did not don safety glasses while using pneumatic nail guns to attach shingles to the roof of a two story residential building and were exposed to flying debris and ricochet nails, on or about December 14, 2023. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.