Violation Detail
Standard Cited: 19100212 A04 General requirements for all machines.
Inspection Nr: 1706288.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,676.00
Current Penalty: $7,605.00
Issuance Date: 03/25/2024
Nr Instances: 5
Nr Exposed: 5
Abatement Date: 12/16/2024
Gravity: 5
Report ID: 0524700
Contest Date:
Final Order: 04/15/2024
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | P: Petition to Mod Abatement | 09/23/2024 | $7,605.00 | 12/16/2024 | Serious | |
Penalty | I: Informal Settlement | 04/15/2024 | $7,605.00 | 08/01/2024 | Serious | |
Penalty | Z: Issued | 03/25/2024 | $12,676.00 | 04/10/2024 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.212(a)(4):Revolving drum(s), barrel(s), or container(s) were not guarded by enclosure(s) which were interlocked with the drive mechanism so that the barrel(s), drum(s), or container(s) could not revolve unless the enclosure(s) were in place: a) HBD Thermoid, Inc. Bellefontaine, Ohio: On or about November 07, 2023, the employer did not ensure the line #5 reeler station cooling drums were enclosed by interlocking guards. In this condition employees were exposed to ingoing nip points created by the two vertically aligned horizontal rotating drums and wound hose being cooled. b) HBD Thermoid, Inc. Bellefontaine, Ohio: On or about October 24, 2023, the employer did not ensure the line #1 reeler station cooling drums were enclosed by interlocking guards. In this condition employees were exposed to ingoing nip points created by the two vertically aligned horizontal rotating drums and wound hose being cooled. c) HBD Thermoid, Inc. Bellefontaine, Ohio: On or about October 24, 2023, the employer did not ensure the line #2 reeler station cooling drums were enclosed by interlocking guards. In this condition employees were exposed to ingoing nip points created by the two vertically aligned horizontal rotating drums and wound hose being cooled. d) HBD Thermoid, Inc. Bellefontaine, Ohio: On or about October 24, 2023, the employer did not ensure the line #7 reeler station cooling drums were enclosed by interlocking guards. In this condition employees were exposed to ingoing nip points created by the two vertically aligned horizontal rotating drums and wound hose being cooled. e) HBD Thermoid, Inc. Bellefontaine, Ohio: On or about October 24, 2023, the employer did not ensure the line #8 reeler station cooling drums were enclosed by interlocking guards. In this condition employees were exposed to ingoing nip points created by the two vertically aligned horizontal rotating drums and wound hose being cooled.