Violation Detail
Standard Cited: 19100269 A03 III Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1684216.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $6,250.00
Current Penalty: $6,250.00
Issuance Date: 01/09/2024
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 02/05/2024
Gravity: 10
Report ID: 0830600
Contest Date:
Final Order: 02/02/2024
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/02/2024 | $6,250.00 | 02/05/2024 | Serious | |
Penalty | Z: Issued | 01/09/2024 | $6,250.00 | 02/05/2024 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.269(a)(3)(iii): The contract employer and the host employer did not coordinate their work rules and procedures so that each employee of the contract employer and the host employer was protected as required by this section: a) On or about July 13, 2023, and at times prior, LND Technical Services, LLC, as a contract employer, did not coordinate or communicate by any means, site-specific, electrical safety work rules and procedures regarding high-voltage testing and maintenance activities in Substation 2, with the host employer, ENSCO, Inc. This exposed employees to electrical hazards.