Violation Detail
Standard Cited: 19260651 J02 Specific Excavation Requirements.
This violation item has been deleted.
Inspection Nr: 1680537.015
Citation: 01003
Citation Type: Serious
Abatement Status:
Initial Penalty: $10,938.00
Current Penalty: $0.00
Issuance Date: 11/28/2023
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 12/06/2023
Gravity: 10
Report ID: 0111400
Contest Date:
Final Order: 12/22/2023
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/22/2023 | $0.00 | 12/06/2023 | Serious | |
Penalty | Z: Issued | 11/28/2023 | $10,938.00 | 12/06/2023 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.651(j)(2):Protection was not provided by placing and keeping excavated or other materials or equipment at least 2 feet (.61m) from the edge of excavations, or by the use of retaining devices that were sufficient to prevent materials or equipment from falling or rolling into excavations, or by a combination of both if necessary. LOCATION: The jobsite at 19 Newport Ave On or about June 29th, 2023 the employees of Sean Farrell Excavation were exposed to struck-by and crush injuries from the spoil piled immediately adjacent to the excavation while working in the trench the spall was adjacent to.