Standard Cited: 19100147 D05 I The control of hazardous energy (lockout/tagout).
This violation item has been deleted.
Inspection Nr: 1644623.015
Citation: 01003
Citation Type: Serious
Abatement Status:
Initial Penalty: $15,625.00
Current Penalty: $0.00
Issuance Date: 04/19/2023
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 05/08/2023
Gravity: 10
Report ID: 0626600
Contest Date:
Final Order: 05/15/2023
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/15/2023 | $0.00 | 05/08/2023 | Serious | |
Penalty | Z: Issued | 04/19/2023 | $15,625.00 | 05/08/2023 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.147(d)(5)(i): Following the application of lockout or tagout devices to energy isolating devices, all potentially hazardous stored or residual energy was not relieved, disconnected, restrained, and otherwise rendered safe: This violation occurred on or about January 13, 2023 in the boiler area. The employer does not ensure that following the application of lockout or tagout devices to energy isolating devices, all potentially hazardous stored or residual energy was relieved, disconnected, restrained, and otherwise rendered safe, this exposed employees to thermal hazards when performing maintenance tasks on the following equipment such as, but not limited to the Supreme boiler, model 8X-2000 with serial number 17536.