Violation Detail
Standard Cited: 19260451 F04 General requirements.
Inspection Nr: 1642989.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,349.00
Current Penalty: $2,000.00
Issuance Date: 06/13/2023
Nr Instances: 1
Nr Exposed: 4
Abatement Date: 07/11/2023
Gravity: 5
Report ID: 0418300
Contest Date:
Final Order: 07/07/2023
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/07/2023 | $2,000.00 | 07/11/2023 | Serious | |
| Penalty | Z: Issued | 06/13/2023 | $3,349.00 | 07/11/2023 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.451(f)(4): Part(s) of a scaffold that were damaged or weakened, such that the scaffold's strength was less than that required by paragraph (a) of this section, were not immediately repaired, replaced, braced to meet those provisions, nor removed from service until repaired: (a) On or about January 05, 2023 and at times prior to - Building 4, employees were exposed to fall hazards of up to approximately 30 feet when bent cross braces were used.