Standard Cited: 19260651 J02 Specific Excavation Requirements.
Inspection Nr: 1612739.015
Citation: 01003
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $6,215.00
Current Penalty: $6,215.00
Issuance Date: 09/19/2022
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity: 1
Report ID: 0625500
Contest Date: 10/13/2022
Final Order: 07/07/2023
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/07/2023 | $6,215.00 | Other | ||
Penalty | C: Contested | 10/17/2022 | $6,215.00 | Serious | ||
Penalty | Z: Issued | 09/19/2022 | $6,215.00 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.651(j)(2):Protection was not provided by placing and keeping excavated or other materials or equipment at least 2 feet (.61m) from the edge of excavations, or by the use of retaining devices that were sufficient to prevent materials or equipment from falling or rolling into excavations, or by a combination of both if necessary: Corner of Zeke and Galm Rd, San Antonio, TX 78254: On or about August 2, 2022, and times prior thereto, employees were exposed to a struck-by hazard while conducting maintenance on a main gas line excavation with spoil piles located less than 2 feet from the edge of the excavation walls.