Violation Detail
Standard Cited: 19260850 A Preparatory operations.
This violation item has been deleted.
Inspection Nr: 1593860.015
Citation: 01003
Citation Type: Serious
Abatement Status:
Initial Penalty: $14,502.00
Current Penalty: $0.00
Issuance Date: 11/01/2022
Nr Instances: 1
Nr Exposed: 8
Abatement Date: 11/16/2022
Gravity: 10
Report ID: 0111400
Contest Date: 11/28/2022
Final Order: 07/20/2023
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/20/2023 | $0.00 | 11/16/2022 | Serious | |
Penalty | C: Contested | 11/29/2022 | $14,502.00 | 11/16/2022 | Serious | |
Penalty | Z: Issued | 11/01/2022 | $14,502.00 | 11/16/2022 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.850(a): Prior to permitting employees to start demolition operations, an engineering survey was not made by a competent person of the structure to determine the condition of the framing, floors, and walls, and possibility of unplanned collapse of any portion of the structure, including adjacent structures where employees may be exposed. The employer did not have in writing evidence that such a survey was performed. Location: Worksite On May 4, 2022, three NorthStar employees were injured when a concrete mezzanine platform unexpectedly collapsed during demolition and abatement operations. One employee suffered a double leg imputation. On or about May 4 2022, Suffolk Construction did not have a plan in place to prevent an unplanned collapse of the Building 1A west wall mezzanine.