Violation Detail
Standard Cited: 19100269 D02 IV Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 1591289.015
Citation: 01003
Citation Type: Serious
Abatement Status:
Initial Penalty: $14,502.00
Current Penalty: $0.00
Issuance Date: 10/06/2022
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 11/01/2022
Gravity: 10
Report ID: 0112300
Contest Date: 10/31/2022
Final Order: 06/12/2023
Related Event Code (REC): I;R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 06/12/2023 | $0.00 | 11/01/2022 | Serious | |
Penalty | C: Contested | 11/01/2022 | $14,502.00 | 11/01/2022 | Serious | |
Penalty | Z: Issued | 10/06/2022 | $14,502.00 | 11/01/2022 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.269(d)(2)(iv): The procedure did not clearly and specifically outline the scope, purpose, responsibility, authorization, rules, and techniques to be applied to the control of hazardous energy, and the measures to enforce compliance including, but not limited to the following: (a) Manchester Street Station - Generator #10: On or about 4/21/2022, the employer did not have a written procedure that clearly and specifically outlined the scope, purpose, rules and techniques to control hazardous energy, while servicing power generation equipment, and the measures to enforce compliance, exposing employees to electrical shock hazards.