Violation Detail
Standard Cited: 19100212 A01 General requirements for all machines.
This violation item has been deleted.
Inspection Nr: 1565302.015
Citation: 01003
Citation Type: Serious
Abatement Status:
Initial Penalty: $10,360.00
Current Penalty: $0.00
Issuance Date: 02/10/2022
Nr Instances: 1
Nr Exposed: 15
Abatement Date: 02/22/2022
Gravity: 5
Report ID: 0316700
Contest Date: 03/07/2022
Final Order: 04/04/2022
Related Event Code (REC): C
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | C: Contested | 07/21/2022 | $10,360.00 | 02/22/2022 | Serious | |
| Penalty | F: Formal Settlement | 04/04/2022 | $0.00 | 02/22/2022 | Serious | |
| Penalty | Z: Issued | 02/10/2022 | $10,360.00 | 02/22/2022 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.212(a)(1): Machine guarding was not provided to protect operator(s) and other employees from hazard(s) created by ingoing nip point and shear points a. Production line 5 - On or about November 23, 2021, the flight conveyor system had unguarded nip point and shear points where the interior side of the conveyor slats entered back into the closed section of the conveyor system, exposing employees to a caught in hazard. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.