Violation Detail
Standard Cited: 19100252 A02 IV General requirements.
Inspection Nr: 1485438.015
Citation: 01003
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $9,446.00
Current Penalty: $2,500.00
Issuance Date: 01/13/2021
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 03/03/2021
Gravity: 10
Report ID: 0524200
Contest Date:
Final Order: 02/09/2021
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | P: Petition to Mod Abatement | 02/26/2021 | $2,500.00 | 03/03/2021 | Other | |
Penalty | I: Informal Settlement | 02/09/2021 | $2,500.00 | 03/03/2021 | Other | |
Penalty | Z: Issued | 01/13/2021 | $9,446.00 | 02/17/2021 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.252(a)(2)(iv): The individual responsible for authorizing cutting or welding operations did not designate precautions to be followed in granting authorization to proceed preferably in the form of a written permit: a) On or about, July 28, 2020 Chicago Boiler Company dba CB Mills Division of Chicago Boiler Company, the employer did not ensure that the entry conditions were verified and met, or complete a written permit, prior to employees performing welding inside tanks. In accordance with 29 CFR 1903.19 (d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstration that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of purchase or repair of equipment, photographic or video evidence of abatement or other written records.