Violation Detail
Standard Cited: 19100036 G04 Design and construction requirements for exit routes.
Inspection Nr: 1477553.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,145.00
Current Penalty: $12,145.00
Issuance Date: 12/01/2020
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 12/28/2020
Gravity: 10
Report ID: 0317300
Contest Date: 12/11/2020
Final Order: 09/07/2021
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 09/07/2021 | $12,145.00 | 12/28/2020 | Serious | |
Penalty | C: Contested | 02/24/2021 | $12,145.00 | 12/28/2020 | Serious | |
Penalty | Z: Issued | 12/01/2020 | $12,145.00 | 12/28/2020 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.36(g)(4): Objects projecting into the exit route reduced the width of the exit route to less than the minimum width requirements for exit routes: a) 701 Pencader Drive #F Newark, DE - On or about June 2, 2020, employees worked at a Husker manufactured Winor cocoa bean processing machine in the production area of the facility where the exit access was not at least 28 inches wide at all points.