Violation Detail
Standard Cited: 19100219 C04 I Mechanical power-transmission apparatus.
Inspection Nr: 1453449.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,725.00
Current Penalty: $4,007.00
Issuance Date: 05/27/2020
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 06/10/2020
Gravity: 1
Report ID: 0523900
Contest Date:
Final Order: 06/22/2020
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/22/2020 | $4,007.00 | 06/10/2020 | Serious | |
Penalty | Z: Issued | 05/27/2020 | $5,725.00 | 06/10/2020 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.219(c)(4)(i): Unguarded projecting shaft end(s) did not present a smooth edge and projected more than one half the diameter of the shaft: (a) Fiber filling area; The ends of eight unguarded protruding shafts were not smooth and projected more than one-half the diameter of the shaft on a Carolina Machinery Company brand fiber filling machine (EF-38-4).