Violation Detail
Standard Cited: 19100212 A01 General requirements for all machines.
Inspection Nr: 1448440.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,899.00
Current Penalty: $4,129.30
Issuance Date: 01/27/2020
Nr Instances: 1
Nr Exposed: 3
Abatement Date: 03/13/2020
Gravity: 5
Report ID: 0112000
Contest Date:
Final Order: 02/23/2020
Related Event Code (REC): C
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/23/2020 | $4,129.30 | 03/13/2020 | Serious | |
| Penalty | Z: Issued | 01/27/2020 | $5,899.00 | 03/13/2020 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.212(a)(1): One or more methods of machine guarding was not provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, ingoing nip points, rotating parts, flying chips and sparks: Boiler room rear area: On or about December 3, 2019, an air compressor used to augment the sprinkler system pressure was unguarded. There was a two foot by 19 inch opening to the spoked pulley located on the floor. Possible amputations, crush injuries, or avulsions are possible if an employees hand would get caught the compressor.