Standard Cited: 19260703 A01 Requirements for cast-in-place Concrete.
Inspection Nr: 1447797.015
Citation: 01003
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $13,494.00
Current Penalty: $13,494.00
Issuance Date: 05/18/2020
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC): A
Gravity: 10
Report ID: 0522000
Contest Date:
Final Order: 06/12/2020
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/12/2020 | $13,494.00 | Serious | ||
Penalty | Z: Issued | 05/18/2020 | $13,494.00 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.703(a)(1): "General requirements for formwork." Formwork shall be designed, fabricated, erected, supported, braced and maintained so that it will be capable of supporting without failure all vertical and lateral loads that may reasonably be anticipated to be applied to the formwork. Formwork which is designed, fabricated, erected, supported, braced and maintained in conformance with the Appendix to this section will be deemed to meet the requirements of this paragraph. During construction of the 7th floor of the parking garage located at Fourth and Race, the employer failed to adequately review initial and revised shoring plans provided by outside engineering firms to account for additional loads imposed by a 24" slab section of that floor.