Violation Detail
Standard Cited: 19100305 G01 IV B Wiring methods, components, and equipment for general use.
Inspection Nr: 1409524.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $3,978.00
Current Penalty: $2,467.00
Issuance Date: 10/15/2019
Nr Instances: 1
Nr Exposed: 15
Abatement Date: 10/25/2019
Gravity: 1
Report ID: 0213900
Contest Date:
Final Order: 11/12/2019
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 11/12/2019 | $2,467.00 | 10/25/2019 | Serious | |
| Penalty | Z: Issued | 10/15/2019 | $3,978.00 | 10/25/2019 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.305(g)(1)(iv)(B): Flexible cords and/or cables were run through holes in walls, ceilings, or floors: a) Maintenance Shop: A flexible cord in the maintenance shop was being run through a hole in the wall to power a data entry computer in the plant, on or about 6/20/19. NOTE: IN ADDITION TO ABATEMENT CERTIFICATION, THE EMPLOYER IS REQUIRED TO SUBMIT ABATEMENT DOCUMENTATION FOR THIS ITEM. FAILURE TO COMPLY WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00 IN ACCORDANCE WITH 29 CFR 1903.19.
Translate