Violation Detail
Standard Cited: 19260416 A03 General requirements.
Inspection Nr: 1396386.015
Citation: 01003
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $3,410.00
Current Penalty: $2,000.00
Issuance Date: 10/28/2019
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity:
Report ID: 0625500
Contest Date:
Final Order: 09/10/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 09/10/2020 | $2,000.00 | Other | ||
| Penalty | Z: Issued | 10/28/2019 | $3,410.00 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.416(a)(3): Before work began, the employer did not ascertain by inquiry, direct observation, or by instruments, whether any part of an energized electric power circuit, exposed or concealed, was so located that the performance of the work could bring any person, tool, or machine into physical or electrical contact with the electric power circuit: Unit 4, Electrical Panel Box: On May 1, 2019, and at times prior thereto, employees were exposed to an electrical hazard, while installing a blower motor without identifying and testing for live energized circuits.