Violation Detail
Standard Cited: 19260451 D03 VI General requirements.
Inspection Nr: 1388879.015
Citation: 01003
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $6,630.00
Current Penalty: $5,469.00
Issuance Date: 08/19/2019
Nr Instances: 1
Nr Exposed: 2
Abatement Date:
Gravity: 5
Report ID: 0214500
Contest Date: 09/03/2019
Final Order: 03/27/2020
Related Event Code (REC): I
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/27/2020 | $5,469.00 | Serious | ||
Penalty | C: Contested | 09/04/2019 | $6,630.00 | Serious | ||
Penalty | Z: Issued | 08/19/2019 | $6,630.00 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.451(d)(3)(vi): Outrigger beams which are not stabilized by bolts or other direct connections to the floor or roof deck were not secured by tiebacks: a) South Façade - Suspended Scaffold: Employees engaged in masonry activity from a suspended scaffold platform were exposed to fall hazards of approximately 70 feet as the two outrigger beams were not bolted and not tied back, on or about 3/28/19