Violation Detail
Standard Cited: 19100119 J05 Process safety management of highly hazardous chemicals.
Inspection Nr: 1343368.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $10,420.00
Current Penalty: $7,294.00
Issuance Date: 02/26/2019
Nr Instances: 1
Nr Exposed: 28
Abatement Date: 04/01/2019
Gravity: 5
Report ID: 0134000
Contest Date:
Final Order: 03/11/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/11/2019 | $7,294.00 | 04/01/2019 | Serious | |
Penalty | Z: Issued | 02/26/2019 | $10,420.00 | 04/01/2019 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.119(j)(5): The employer did not correct deficiencies in equipment that were outside acceptable limits (defined by the process safety information on paragraph (d) of this section) before use: a) 626 Lynnway, Lynn, MA On or about August 30, and September 13, 2018, failures in the vapor barrier of insulated piping were not repaired. Piping located in the engine room 2 was found to have frost permeating the pipe insulation. Abatement certification is required of this item in accordance with the requirements of 29 CFR 1903.19(d).