Violation Detail
Standard Cited: 19260850 A Preparatory operations.
Inspection Nr: 1335808.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,934.00
Current Penalty: $10,994.00
Issuance Date: 01/18/2019
Nr Instances: 2
Nr Exposed: 3
Abatement Date: 02/14/2019
Gravity: 10
Report ID: 0524530
Contest Date: 02/11/2019
Final Order: 06/27/2019
Related Event Code (REC): A
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 06/27/2019 | $10,994.00 | 02/14/2019 | Serious | |
Penalty | C: Contested | 02/11/2019 | $12,934.00 | 02/14/2019 | Serious | |
Penalty | Z: Issued | 01/18/2019 | $12,934.00 | 02/14/2019 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.850(a): An engineering survey was not performed by a competent person to determine the conditions of the framing floors and walls and the possibility of unplanned collapse of any portion of the structure prior to permitting employees to start demolition operations: a. On or about July 18, 2018, employees were permitted to conduct demolition operations and an Engineering Survey had not been performed to determine the conditions of the four story east wall and the possibility of unplanned collapse of the structure. b. On or about August 1, 2018, employees were permitted to conduct demolition operations and an Engineering Survey had not been performed to determine the conditions of the north wall and the possibility of unplanned collapse of the structure.