Violation Detail
Standard Cited: 19260452 W01 Additional requirements applicable to specific types of scaffolds.
Inspection Nr: 1319225.015
Citation: 01003
Citation Type: Serious
Abatement Date: 07/18/2018 4
Initial Penalty: $3,880.00
Current Penalty: $750.00
Issuance Date: 06/28/2018
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): R
Gravity: 10
Report ID: 0522000
Contest Date:
Final Order: 07/24/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/24/2018 | $750.00 | 07/18/2018 | Serious | |
Penalty | Z: Issued | 06/28/2018 | $3,880.00 | 07/18/2018 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.452(w)(1): Scaffolds shall be braced by cross, horizontal, or diagonal braces, or combination thereof, to prevent racking or collapse of the scaffold and to secure vertical members together laterally so as to automatically square and align the vertical members. Scaffolds shall be plumb, level, and squared. All brace connections shall be secured. On May 23, at 206 Vine St, New Boston, a metal storage unit building under construction, a mobile scaffold 2 ft. x 4 ft. x 4 ft. was not braced to prevent the racking and collapse of the scaffold and prevent a fall hazard to the Laborer while the Laborer was on the working platform with a missing metal plank on the scaffold to install metal corrugated siding on the interior wall of a storage unit compartment.