Standard Cited: 19100269 D02 III Electric Power Generation, Transmission, and Distribution.

This violation item has been deleted.

Inspection Nr: 1285745.015

Citation: 01003

Citation Type: Serious

Abatement Status:  

Initial Penalty: $12,934.00

Current Penalty: $0.00

Issuance Date: 04/17/2018

Nr Instances: 1

Nr Exposed: 1

Abatement Date: 05/04/2018

Gravity: 10

Report ID: 0112600

Contest Date: 05/15/2018

Final Order: 09/16/2019

Related Event Code (REC): R

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty F: Formal Settlement 09/16/2019 $0.00 05/04/2018 Serious  
Penalty C: Contested 05/16/2018 $12,934.00 05/04/2018 Serious  
Penalty Z: Issued 04/17/2018 $12,934.00 05/04/2018 Serious  

Text For Citation: 01 Item/Group: 003 Hazard:

29 CFR 1910.269(d)(2)(iii): Procedures were not developed, documented, and used for the control of potentially hazardous energy covered by paragraph (d) of this section: Tesla, Inc., Hampshire College MV Metering Panel, Amherst, Massachusetts; On or about December 29, 2017, employees were exposed to 13,800 volts while entering an energized panel to take pictures of the current transformers without utilizing the hazardous energy control procedure for the equipment.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.