Violation Detail
Standard Cited: 19100219 F03 Mechanical power-transmission apparatus.
Inspection Nr: 1275823.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,956.00
Current Penalty: $1,772.00
Issuance Date: 01/10/2018
Nr Instances: 1
Nr Exposed: 13
Abatement Date: 02/05/2018
Gravity: 5
Report ID: 0524700
Contest Date:
Final Order: 01/23/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/23/2018 | $1,772.00 | 02/05/2018 | Serious | |
| Penalty | Z: Issued | 01/10/2018 | $2,956.00 | 02/05/2018 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.219(f)(3): Sprocket wheels and chains which were seven -7 feet or less above floors or platforms were not enclosed: a) On or about November 7, 2017, the employer did not ensure that employees were protected from caught in hazards associated with the unguarded chain and sprocket on the side of the Warco mechanical power press (press #19) that was 77" from the floor. Employees are in the area performing work while the press is in operation.