Violation Detail
Standard Cited: 19100219 C04 I Mechanical power-transmission apparatus.
Inspection Nr: 1258467.015
Citation: 01003
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $11,086.00
Current Penalty: $5,550.00
Issuance Date: 01/19/2018
Nr Instances: 1
Nr Exposed: 2
Abatement Date:
Gravity:
Report ID: 0636900
Contest Date: 02/19/2018
Final Order: 05/02/2019
Related Event Code (REC): C
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | R: Review Commission | 05/02/2019 | $5,550.00 | Other | ||
Penalty | C: Contested | 03/07/2018 | $11,086.00 | Serious | ||
Penalty | Z: Issued | 01/19/2018 | $11,086.00 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.219(c)(4)(i): Unguarded projecting shaft end(s) did not present a smooth edge and end and projected more than one half the diameter of the shaft: a) Lamp Bulb Recycle area: On or about August 30, 2019, the shaft on the lamp bulb recycle equipment projected outward greater than one half the diameter of the shaft.