Violation Detail
Standard Cited: 19260416 A01 General requirements.
Inspection Nr: 1237920.015
Citation: 01003
Citation Type: Serious
Abatement Date: 10/25/2017 2
Initial Penalty: $5,070.00
Current Penalty: $3,802.50
Issuance Date: 10/13/2017
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 10
Report ID: 0215800
Contest Date:
Final Order: 10/25/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/25/2017 | $3,802.50 | 10/25/2017 | Serious | |
Penalty | Z: Issued | 10/13/2017 | $5,070.00 | 10/25/2017 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.416(a)(1): Employees were permitted to work in proximity to electric power circuits and were not protected against electric shock by de-energizing and grounding the circuits or effectively guarding the circuits by insulation or other means: a) On or about 5/22/2017, SUNY Oswego: Employees were performing work on an energized circuit. Abatement documentation is required for this item.