Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1229034.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $12,675.00
Current Penalty: $4,125.00
Issuance Date: 10/31/2017
Nr Instances: 1
Nr Exposed: 25
Abatement Date: 09/25/2018
Gravity: 10
Report ID: 0418100
Contest Date: 11/23/2017
Final Order: 09/04/2018
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 09/04/2018 | $4,125.00 | 09/25/2018 | Serious | |
Penalty | C: Contested | 12/13/2017 | $12,675.00 | 12/19/2017 | Serious | |
Penalty | Z: Issued | 10/31/2017 | $12,675.00 | 12/19/2017 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section. On 5/2/2017, at the Buford facility, employees performing Authorized work at the facility, including but not limited to the Screen Print machine, Ona 90 press, and the CK41 Riveter machine, were not required to utilize established Lockout procedures.