Violation Detail
Standard Cited: 19100243 B02 Guarding of portable powered tools.
Inspection Nr: 1210081.015
Citation: 01003
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $5,577.00
Current Penalty: $3,346.20
Issuance Date: 07/20/2017
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 5
Report ID: 0214500
Contest Date:
Final Order: 10/10/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/10/2017 | $3,346.20 | Serious | ||
Penalty | Z: Issued | 07/20/2017 | $5,577.00 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.243(b)(2): Air hose and hose connections used for conducting compressed air to utilization equipment was not designed for the pressure and service to which they were subjected. a) Eddy Magnetic Separator machine: The air hose used to clean off equipment was attached to a hose fitting which was secured by a worm-driven hose clamp which was not designed for use on an air hose, thereby exposing the employees to the whipping action of the hose if the clamp were to come off, on or about 2/23/2017.