Violation Detail
Standard Cited: 19260403 B01 II General requirements.
Inspection Nr: 1100042.015
Citation: 01003
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,640.00
Current Penalty: $0.00
Issuance Date: 04/01/2016
Nr Instances: 4
Nr Exposed: 4
Abatement Date: 02/11/2017
Gravity: 5
Report ID: 0317700
Contest Date: 04/25/2016
Final Order: 12/28/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 12/28/2016 | $0.00 | 02/11/2017 | Serious | |
Penalty | C: Contested | 04/27/2016 | $2,640.00 | 05/06/2016 | Serious | |
Penalty | Z: Issued | 04/01/2016 | $2,640.00 | 05/06/2016 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.403(b)(1)(ii): Safety of equipment was not determined on the basis of mechanical strength and durability, including, for parts designed to enclose and protect other equipment, the adequacy of the protection thus provided: a) Danville Borough Municipal Authority Storage Site, employees, blasters, were exposed to electric shock hazards in that the 120 VAC light bulbs, mounted on the ends of the blasting nozzles, were not equipped with safety cage or rated enclosure to protect against bulb or housing breakage, on or about October 27, 2015 ABATEMENT CERTIFICATION REQUIRED