Violation Detail
Standard Cited: 19100107 I08 Spray finishing using flammable and combustible materials.
Inspection Nr: 1421123.015
Citation: 01002F
Citation Type: Serious
Abatement Date: 03/06/2020 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 02/10/2020
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): C
Gravity: 10
Report ID: 0317300
Contest Date: 02/27/2020
Final Order: 07/09/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/09/2021 | $0.00 | 03/06/2020 | Serious | |
Penalty | C: Contested | 02/28/2020 | $0.00 | 03/06/2020 | Serious | |
Penalty | Z: Issued | 02/10/2020 | $0.00 | 03/06/2020 | Serious |
Text For Citation: 01 Item/Group: 002F Hazard:
29 CFR 1910.107(i)(8): The electrical equipment was not so interlocked with the ventilation of the spraying area that the equipment cannot be operated unless the ventilation fans are in operation: (a) Painting Area ("Paint Booth") - On or about August 13, 2019, the employer failed to protect employees from potential fire hazards as no provisions were made to interlock electrical equipment and compressed air supplies with the ventilation system so that the equipment cannot be operated unless the ventilation fans are in operation.