Powered by GoogleTranslate

Violation Detail

Standard Cited: 19260251 E01 III Rigging equipment for material handling.

Inspection Nr: 1112039.015

Citation: 01002F

Citation Type: Other

Abatement Status: Not Completed - Worksite Changed

Initial Penalty: $0.00

Current Penalty: $0.00

Issuance Date: 05/25/2016

Nr Instances: 2

Nr Exposed: 1

Abatement Date: 06/03/2016

Gravity:

Report ID: 0111500

Contest Date:

Final Order: 06/22/2016

Related Event Code (REC):

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty I: Informal Settlement 06/22/2016 $0.00 06/03/2016 Other  
Penalty Z: Issued 05/25/2016 $0.00 06/03/2016 Serious  

Text For Citation: 01 Item/Group: 002F Hazard:

29 CFR 1926.251(e)(1)(iii): Synthetic web sling(s) were not marked or coded to show type of material: WORKSITE: The two (2) synthetic web slings, used by employees to lift and carry bundles of rebar using the bucket of the Kobelco Model SK160LC hydraulic excavator were not marked with data plate that identified with the type of material.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.

Close