Violation Detail
Standard Cited: 19100119 L04 Process safety management of highly hazardous chemicals.
Inspection Nr: 314091497
Citation: 01002C
Citation Type: Other
Abatement Status: X
Initial Penalty:
Current Penalty:
Issuance Date: 05/16/2011
Nr Instances: 3
Nr Exposed: 10
Abatement Date: 06/30/2011
Gravity: 05
Report ID: 0418400
Contest Date:
Final Order:
Related Event Code (REC):
Emphasis:
Substance: D177
Substance: 1680
Substance: 0675
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/09/2011 | 06/30/2011 | Other | ||
| Penalty | Z: Issued | 05/16/2011 | 06/30/2011 | Serious |
Text For Citation: 01 Item/Group: 002C Hazard: CHEMNEP
29 CFR 1910.119(l)(4): A change covered by 29 CFR 1910.119(l) resulted in a change in the process safety information required by 29 CFR 1910.119(d) and the process information was not updated: a)DELETED FOR ISA SETTLEMENT. LBD 6.13.2011 b)In the methyl bromide unloading area, on or about February 11, 2011 and at times prior to, the P&ID for the rail connections Figure 3(a) was not updated to include details about the ISO container off load station for the 100% methyl bromide, which had been installed in January 2011, resulting in a chemical hazard. c)In the Telone unloading area, on or about February 11, 2011 and at times prior to, the P&ID for the rail connections Figure 3(a) was not updated to include details about the nitrogen transfer system, following the change from compressed air to nitrogen in December 2010, resulting in fire and chemical hazards. ABATEMENT CERTIFICATION IS REQUIRED.TION