Violation Detail
Standard Cited: 19100119 D03 I D Process safety management of highly hazardous chemicals.
Inspection Nr: 1633713.015
Citation: 01002C
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/10/2023
Nr Instances: 5
Nr Exposed: 6
Abatement Date: 05/30/2023
Gravity: 10
Report ID: 0636900
Contest Date:
Final Order: 05/03/2023
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/03/2023 | $0.00 | 05/30/2023 | Serious | |
| Penalty | Z: Issued | 04/10/2023 | $0.00 | 05/30/2023 | Serious |
Text For Citation: 01 Item/Group: 002C Hazard:
29 CFR 1910.119(d)(3)(i)(D): Process safety information (PSI) pertaining to the equipment in the process did not include relief system design and design basis. On or about 11/10/2022, at the Schirm facility located in Ennis Texas, employees were exposed to chemicals release hazards when the employer did not document relief system design and design basis for pressure relieve valves including but not limited to: a) The employer did not document relief system design and design basis for two (2) pressure relieve valves on the top of isopropylamine (IPA) tank. b) The employer did not document relief system design and design basis for the pressure relieve valve PRV-01 on the top of Reactor R-1. c) The employer did not document relief system design and design basis for the pressure relieve valve PRV-02 on the top of Reactor R-2. d) The employer did not document relief system design and design basis for a pressure relieve on a discharge pipe of the isopropylamine pump P-02. e) The employer did not document relief system design and design basis for a pressure relieve on a discharge pipe of the isopropylamine pump P-03.