Violation Detail
Standard Cited: 19100147 D03 The control of hazardous energy (lockout/tagout).
Inspection Nr: 978621.015
Citation: 01002B
Citation Type: Serious
Abatement Date: 09/23/2014 2
Initial Penalty: $2,800.00
Current Penalty: $0.00
Issuance Date: 08/27/2014
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 5
Report ID: 0523400
Contest Date:
Final Order: 09/16/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/16/2014 | $0.00 | 09/23/2014 | Serious | |
Penalty | Z: Issued | 08/27/2014 | $2,800.00 | 09/23/2014 | Serious |
Text For Citation: 01 Item/Group: 002B Hazard:
29 CFR 1910.147(d)(3): All energy isolating devices that were needed to control the energy to the machine or equipment were not physically located and operated in such a manner as to isolate the machine or equipment from the energy source(s): (a) On the Main Level, conveyor CP Manufacturing, Inc. (Model: 9026630) toggle switches were used as an energy isolating device. This exposed employees to accidental / inadvertent restart of equipment. (b) The Sebright Products Inc. compactor (S/N: 11 08 10637) selector switch was used as an energy isolating device. This exposed employees to accidental / inadvertent restart of equipment.