Violation Detail
Standard Cited: 19100023 E01 Ladders.
Inspection Nr: 942073.015
Citation: 01002B
Citation Type: Serious
Abatement Date: 02/04/2014 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 01/30/2014
Nr Instances: 2
Nr Exposed: 2
Related Event Code (REC):
Gravity: 5
Report ID: 0419400
Contest Date:
Final Order: 02/18/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/18/2014 | $0.00 | 02/04/2014 | Serious | |
Penalty | Z: Issued | 01/30/2014 | $0.00 | 02/04/2014 | Serious |
Text For Citation: 01 Item/Group: 002B Hazard:
29 CFR 1910.23(e)(1): A standard railing shall consist of top rail, intermediate rail, and posts, and shall have a vertical height of 42 inches nominal from upper surface of top rail to floor, platform, runway, or ramp level. The top rail shall be smooth-surfaced throughout the length of the railing. The intermediate rail shall be approximately halfway between the top rail and the floor, platform, runway, or ramp. The ends of the rails shall not overhang the terminal posts except where such overhang does not constitute a projection hazard. a) On or about September 19, 2013 the stairs to the loading platform in the Set Up/Mixing Area was not equipped with a midrail.