Violation Detail
Standard Cited: 19100252 A03 II General requirements.
Inspection Nr: 1411493.015
Citation: 01002B
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/24/2019
Nr Instances: 1
Nr Exposed: 20
Abatement Date: 08/13/2019
Gravity:
Report ID: 0625700
Contest Date: 08/16/2019
Final Order: 05/12/2020
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | J: ALJ Decision | 05/12/2020 | $0.00 | 08/13/2019 | Other | |
| Penalty | C: Contested | 04/28/2020 | $0.00 | 08/13/2019 | Serious | |
| Penalty | Z: Issued | 07/24/2019 | $0.00 | 08/13/2019 | Serious |
Text For Citation: 01 Item/Group: 002B Hazard:
29 CFR 1910.252(a)(3)(ii): All hollow spaces, cavities, or containers were not vented to permit the escape of air or gases before preheating, cutting, or welding was performed: a) On or about June 24, 2019, in the Welding shop where new fuel tanks were recently fitted with used fuel pumps, the employer failed to ensure employees vented tanks of combustible gases before welding was performed, which resulted in the injury of an employee.
Translate