Violation Detail
Standard Cited: 19100219 C04 I Mechanical power-transmission apparatus.
Inspection Nr: 1398061.015
Citation: 01002B
Citation Type: Serious
Abatement Date: 08/05/2019 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 06/20/2019
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): C
Gravity: 5
Report ID: 0419400
Contest Date:
Final Order: 07/16/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/16/2019 | $0.00 | 08/05/2019 | Serious | |
Penalty | Z: Issued | 06/20/2019 | $0.00 | 08/05/2019 | Serious |
Text For Citation: 01 Item/Group: 002B Hazard:
29 CFR 1910.219(c)(4)(i): Unguarded projecting shaft end(s) did not present a smooth edge and end and projected more than one half the diameter of the shaft. (a) Planer/Rip Facility - On or about April 30, 2019, The employer did not ensure that a rotating shaft end at the end of transfer conveyor was adequately guarded, exposing employees to a caught-in hazard.