Standard Cited: 19100333 B02 II A Selection and use of work practices
Inspection Nr: 1309949.015
Citation: 01002B
Citation Type: Other
Abatement Date: 07/06/2019 5
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/17/2018
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity:
Report ID: 0522500
Contest Date: 07/27/2018
Final Order: 05/06/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 05/06/2019 | $0.00 | 07/06/2019 | Other | |
Penalty | C: Contested | 08/02/2018 | $0.00 | 08/06/2018 | Serious | |
Penalty | Z: Issued | 07/17/2018 | $0.00 | 08/06/2018 | Serious |
Text For Citation: 01 Item/Group: 002B Hazard:
29 CFR 1910.333(b)(2)(ii)(A): Safe procedures for deenergizing circuits and equipment shall be determined before circuits or equipment are deenergized. a. On or about April 14, 2018, located in the substations, employees were performing preventative maintenance inside five electrical distribution switchboards, 120-13,200 VAC. The employer did not ensure that energy control procedures were developed and utilized to ensure that 1910.333(a)-(c) work practices were employed, such as, but not limited to, reviewing electrical circuits, determining electrical personal protective equipment requirements, procedures for verification of de-energized parts, use and application of grounding equipment, and application of lockout devices by exposed employees.