Violation Detail
Standard Cited: 19100107 B09 Spray finishing using flammable and combustible materials.
Inspection Nr: 1308345.015
Citation: 01002B
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 09/21/2018
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 03/25/2019
Gravity: 5
Report ID: 0316700
Contest Date: 10/12/2018
Final Order: 01/09/2019
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/09/2019 | $0.00 | 03/25/2019 | Serious | |
Penalty | C: Contested | 10/15/2018 | $0.00 | 03/25/2019 | Serious | |
Penalty | Z: Issued | 09/21/2018 | $0.00 | 03/25/2019 | Serious |
Text For Citation: 01 Item/Group: 002B Hazard:
29 CFR 1910.107(b)(9): A clear space of not less than 3 feet on all sides was not kept free from storage or combustible construction: (a) Powder Coating Operation - The Number One Powder Coating room had wooden shelves with cardboard boxes on one side, cardboard boxes on the top of the room and ladders and cardboard boxes on the other side of the spray room, on or about April 11, 2018. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.